2022 Construction Updates
2022 Street Improvements Contract
CLICK HERE FOR CONSTRUCTION MAP
Subsection #1:
- Sidewalk will be installed on Birch Street. Notifications have been sent to adjacent residents.
- Removals on this area started July 14, 2022
- Paving was completed on July 25, 2022
- Structure adjustments are complete.
- Sidewalk at the intersection of Birch and North Liberty requires additional work.
- Restoration is in progress
Subsection #2:
- Construction will start June 13, 2022
- Concrete curb removals are started.
- Concret curb and gutter is planned for the week of June 20, 2022
- Driveway approaches, sidewalk, curb and gutter will be complete on June 23, 2022
- Milling occured June 23, 2022
- Paving occurred June 24, 2022
- Structure adjustments are complete.
- Restoration is in progress.
Subsection #3:
- E Green Street has been moved into subsection #3 so that work on this section can be completed prior to school starting in late August. See updated map at link above.
- Concrete removals have begun in this section.
- Sidewalk will be installed on Locust street. Notifications have been sent to nearby residents.
- Concrete curb and gutter improvements will continue the week of July 4, 2022.
- Concrete installation on Hanover is complete. Open to traffic on July 3, 2022.
- Concrete sidewalk installation started on Locust on June 30. Concrete is expected the week of July 4.
- Milling was completed July 7, 2022
- Paving was completed July 11, 2022
- Structure adjustments are nearly complete.
- Concrete sidewalk still needs to be completed on the east end of the 600 block of E Hanover.
Subsection #4:
- Concrete removals have been started.
- Paving date has not yet been determined
Subsection #5:
- Milling occured on May 19, 2022.
- Concrete work is complete.
- Paving was completed June 1, 2022.
- Manhole structure adjustments are complete.
- Restoration has been completed and will be monitored for establishment.
- The punchlist walkthrough is complete - contractor will be working in the area to complete remaining work.
Subsection #6:
- Milling occured on May 12, 2022.
- Concrete work occured week of May 16, 2022.
- Paving was completed on May 20, 2022.
- Manhole structure adjustments are complete.
- Restoration has been completed and will be monitored for establishment.
- The punchlist walkthrough is complete - contractor will be working in the area to complete remaining work.
Subsection #7:
- Concrete removals started June 1, 2022
- Milling scheduled for June 7, 2022
- Concrete approaches started June 1, 2022
- Paving was completed on June 10, 2022
- Manhole structure adjustments are complete
- Restoration has been started.
Prospect Street Watermain Replacement and Improvements
CLICK HERE FOR CONSTRUCTION MAP
CLICK HERE FOR TRASH PICKUP LOCATIONS
W Prospect; Verona to North Linden - Watermain Replacement and Reconstruction
W Prospect; North Mulberry to North Eagle - Watermain Replacement and Reconstruction
100 Block of W Prospect:
- Concrete driveways can now be accessed and driven on
- Asphalt was installed on June 24, 2022
- Due to construction at Eagle and Prospect - residents should access there homes from Division Drive end of the block
- Top layer of paving is planned for August 10, 2022
200 Block of W Prospect:
- Granger will pickup up curbside carts for the 200 block of W Prospect near 217 N Grand while the road is under construction
- Tentative start date is June 20, 2022. Contractor will move from Eagle Street to the west on W Prospect.
- The intersection of Eagle and Prospect is open for local residents
- The valve installation scheduled for June 29 is complete.
- Watermain installation is complete.
- The watermain passed all testing.
- Water service installations are complete.
300 Block of W Prospect:
- Granger will pickup up curbside carts near 217 N Grand while the road is under construction
- Watermain installation is complete
- The watermain passed all testing.
- Water service installations are complete.
400 Block of W Prospect:
- Granger will pickup up curbside carts near 226 N Sycamore while the road is under construction.
- Watermain installation is complete.
- Testing will occur after watermain is installed in the intersection of N Kalamazoo and Prospect - anticipated for the week of August 8, 2022
E Prospect; North Division to North Madison - Full Reconstruction:
- Milling was cancelled for 5/19/22 and will no longer occur.
- Removal of the street is scheduled to start May 31, 2022.
- Concrete curb is complete.
- Concrete driveways are planned to be installed June 7 and June 8
- Base paving was completed on June 10, 2022
- Restoration has been started.
- Top layer of paving is planned for August 10, 2022.
last updated 8/1/22