2022 Construction Updates

  2022 Street Improvements Contract 

CLICK HERE FOR CONSTRUCTION MAP

Subsection #1: 

  • Sidewalk will be installed on Birch Street. Notifications have been sent to adjacent residents. 
  • Removals on this area started July 14, 2022
  • Paving was completed on July 25, 2022
  • Structure adjustments are complete.
  • Sidewalk at the intersection of Birch and North Liberty requires additional work.
  • Restoration is in progress

Subsection #2: 

  • Construction will start June 13, 2022
  • Concrete curb removals are started.
  • Concret curb and gutter is planned for the week of June 20, 2022
  • Driveway approaches, sidewalk, curb and gutter will be complete on June 23, 2022
  • Milling occured June 23, 2022
  • Paving occurred June 24, 2022
  • Structure adjustments are complete.
  • Restoration is in progress.

Subsection #3:

  • E Green Street has been moved into subsection #3 so that work on this section can be completed prior to school starting in late August. See updated map at link above.
  • Concrete removals have begun in this section.
  • Sidewalk will be installed on Locust street. Notifications have been sent to nearby residents. 
  • Concrete curb and gutter improvements will continue the week of July 4, 2022.
  • Concrete installation on Hanover is complete. Open to traffic on July 3, 2022.
  • Concrete sidewalk installation started on Locust on June 30. Concrete is expected the week of July 4. 
  • Milling was completed July 7, 2022
  • Paving was completed July 11, 2022
  • Structure adjustments are nearly complete.
  • Concrete sidewalk still needs to be completed on the east end of the 600 block of E Hanover. 

Subsection #4: 

  • Concrete removals have been started.
  • Paving date has not yet been determined

Subsection #5:

  • Milling occured on May 19, 2022.
  • Concrete work is complete.
  • Paving was completed June 1, 2022.
  • Manhole structure adjustments are complete.
  • Restoration has been completed and will be monitored for establishment.
  • The punchlist walkthrough is complete - contractor will be working in the area to complete remaining work.

Subsection #6:

  • Milling occured on May 12, 2022. 
  • Concrete work occured week of May 16, 2022.
  • Paving was completed on May 20, 2022.
  • Manhole structure adjustments are complete.
  • Restoration has been completed and will be monitored for establishment.
  • The punchlist walkthrough is complete - contractor will be working in the area to complete remaining work.

Subsection #7: 

  • Concrete removals started June 1, 2022
  • Milling scheduled for June 7, 2022
  • Concrete approaches started June 1, 2022
  • Paving was completed on June 10, 2022
  • Manhole structure adjustments are complete
  • Restoration has been started.

 

  Prospect Street Watermain Replacement and Improvements

CLICK HERE FOR CONSTRUCTION MAP

CLICK HERE FOR TRASH PICKUP LOCATIONS

W Prospect; Verona to North Linden - Watermain Replacement and Reconstruction

  • No update

W Prospect; North Mulberry to North Eagle - Watermain Replacement and Reconstruction

100 Block of W Prospect:

  • Concrete driveways can now be accessed and driven on
  • Asphalt was installed on June 24, 2022
  • Due to construction at Eagle and Prospect - residents should access there homes from Division Drive end of the block
  • Top layer of paving is planned for August 10, 2022

200 Block of W Prospect:

  • Granger will pickup up curbside carts for the 200 block of W Prospect near 217 N Grand while the road is under construction
  • Tentative start date is June 20, 2022. Contractor will move from Eagle Street to the west on W Prospect.
  • The intersection of Eagle and Prospect is open for local residents
  • The valve installation scheduled for June 29 is complete.
  • Watermain installation is complete.
  • The watermain passed all testing.
  • Water service installations are complete.

300 Block of W Prospect:

  • Granger will pickup up curbside carts near 217 N Grand while the road is under construction
  • Watermain installation is complete
  • The watermain passed all testing.
  • Water service installations are complete.

400 Block of W Prospect:

  • Granger will pickup up curbside carts near 226 N Sycamore while the road is under construction.
  • Watermain installation is complete.
  • Testing will occur after watermain is installed in the intersection of N Kalamazoo and Prospect - anticipated for the week of August 8, 2022

E Prospect; North Division to North Madison - Full Reconstruction:

  • Milling was cancelled for 5/19/22 and will no longer occur.
  • Removal of the street is scheduled to start May 31, 2022.
  • Concrete curb is complete.
  • Concrete driveways are planned to be installed June 7 and June 8
  • Base paving was completed on June 10, 2022
  • Restoration has been started.
  • Top layer of paving is planned for August 10, 2022.

last updated 8/1/22 